Airport Drive Subsurface Repair

Airport Drive Subsurface Repair Project Map

Project Location Map
This project proposes to repair a subsurface issue on Airport Drive just west of Canterbury Lane. Subsurface stabilization occurred September 12, 2017. The construction contract for asphalt overlay and sidewalk, curbs, and gutters reconstruction has been awarded and is anticipated to start June 4, 2018.

Project Update for June 15, 2018



  • The remaining items to be completed on this project are as follows:
    • Beginning week of June 18th, 2018 - Paving, striping and seeding to be completed and is weather dependent.  Again, normal traffic flow will be restricted to one (1) lane in each direction. 
  • Ongoing monitoring efforts will continue following construction to ensure road stability.
Please contact Cody Swan at 360 778-6265 with any question regarding this project. In his absence contact Jim Karcher at 360 778-6271.

 
​Project Update for April 20, 2018 


Deep foam injections were completed on September 20, 2017 by the contractor.

The remaining items to be completed on this project are as follows:

  • Utility line repairs including installation of manhole-construction will restrict normal traffic flow anticipated around April/May 2018.
  • Paving overlay and sidewalk reconstruction-Scheduled for late May 2018.
  • Ongoing monitoring efforts will continue following construction to ensure road stability.
Please contact Cody Swan at 360 778-6265 with any questions regarding this project. In his absence contact Jim Karcher at 360 778-6271.