Status-June 30, 2020
Project Summary
This project proposes to install centerline channelization devices 100-feet on the east side of the railroad tracks and 20-feet on the west side of the tracks at the Cove Road crossing. The centerline channelization devices will provide supplemental safety and mitigate for the loss of the train horn once a quiet zone is established. The project will also include shoulder maintenance and upgrades to the railroad crossing warning lights.
Project Details
Status: This project has been delayed due to the reduction in County staff as a result of COVID 19. The County is anticipating construction to begin late summer
Contract Awarded: Whatcom County requested quotes from 4 companies and awarded June 24, 2020
Contract Amount: $10,933.63
Contractor: Kamps Painting