Project Description
The Lake Whatcom Comprehensive Stormwater Plan identifies the area surrounding Edgewater Lane as an area for stormwater improvements. This project will provide water quality improvements by constructing a stormwater vault and new storm pipe to reduce phosphorus loading of Lake Whatcom. This new stormwater vault will be approximately 8-ft x 12-ft and the new 18" stormwater pipe extending approximately 600 feet along Northshore Drive.
Aerial Map
Project Schedule
The project was awarded to Colacurcio Brothers, Inc. through a competitive bid process in the amount of $251,613.67. Construction will begin August 10, 2020 and continue for approximately five weeks, weather dependent.
Traffic will often be reduced to one lane along Northshore Drive, with flagged traffic control. Working hours will be approximately 7:00 AM to 5:00 PM. Motorists should expect minor delays.