Leeward Way Drainage Improvements

Leeward Way Project Location

Project Description

  
Due to poor surface water drainage along Leeward Way, this project will provide a new drainage system to collect the surface water, route the stormwater through approximately 300 feet of new drain pipe, and discharge the water through a new outfall to Lummi Bay.

Project Schedule


The project construction is planned to start October 2020 and should take about five weeks to complete.
Construction Year: October/December 2020

Engineer of Record: Tetra Tech, Inc.

Contractor: Henifin Construction 

Construction Contract Amount: $229,270









​Project Update 10.19.20

Henifin Construction will start work on Monday, October 26, 2020. A portion of Leeward Way will close from 7:00 am to 7:00 pm on weekdays starting Monday, October 26, 2020 through Friday, December 4, 2020. The closure will be approximately 150-feet north of Southgate Road. Crews will install a storm pipe to improve water drainage.