Birch Bay Lynden Road Paving – Enterprise Rd. to Rathbone Rd.

Summary

This project will repave about two miles of Birch Bay Lynden Road between Enterprise and Rathbone roads, and add rumble strips and new pavement markings. There will be single-lane closures and significant travel delays.

  • This project is expected to start Aug. 4 and continue for about a month.
  • Drivers should expect single-lane closures and significant delays.
  • Please avoid the area if possible.

Update: 

  • This project was completed on Sept. 15, 2021. Thank you for your patience during this project! 

Contact Us

  1. Cody Swan

    Project Engineer
    360-778-6265
    [email protected]      
      
    322 N Commercial Street
    Suite 301
    Bellingham, WA 98225
     
    Phone: 360-778-6210
    Fax: 360-778-6211


Project Overview:

  • Status: Contract awarded.
  • Next Steps: Construction.
  • Schedule: This project is expected to start Aug. 2 and continue for about a month.
  • Construction Contractor: Granite Construction 
  • Contract Amount: $909,770.00