Poor weather conditions postponed gravel paving between Lora Lane and the Bay Breeze Restaurant previously scheduled for Sept. 22-23. The week of Sept. 28 construction work will be from 5am-5pm. Granite will install stormwater catch basins along the western side of Birch Bay Drive, along with some other work on the western side of the road. Some work may involve installing pipes across the road with car ramps that allow drivers to pass over the pipes without driving on them. Please drive S-L-O-W when crossing these ramps. Motorcycles and bicycles should use extreme caution on these ramps.
We also want to remind everyone to stay away from construction work and give these workers the appropriate amount of space to get their jobs done safely while building your berm. Please cross over to the east side of the street rather than walk close to the construction project. Birch Bay is a is a beautiful place and we want you to be able to enjoy it safely.