Posted on: November 30, 2020Birch Bay Drive update for the week of Nov. 30-Dec. 4
Nov. 30-Dec. 4 contractor crews will work both days and nights. Day shift 7am-5pm working on plantings and sidewalks, minimal traffic impacts. Night shift 4pm-2am importing gravel to place on the berm, with single-lane closures during those times.