Whatcom County Public works has executed a final design contract with our consultant, Transpo, and is in the process of designing the multi-lane roundabout improvement for the intersection. We have completed our geotechnical explorations, environmental assessments, and survey work at the intersection and are currently working towards a 60% design of the roundabout.
In the weeks and months ahead you may see Public Works staff and consultants on-site gathering additional information about the location that will assist in the design. Construction is currently planned for the summer of 2021.