Expect Delays Starting Aug. 2 on Birch Bay-Lynden Road for Paving Project

Paving on Birch Bay-Lynden Road between Enterprise and Rathbone roads starts Aug. 2. Drivers should expect long delays and avoid the area if possible.

The preliminary schedule for paving Birch Bay-Lynden Road is below: 

  • Week 1 Aug. 2-6: Clear vegetation, remove curb, asphalt planning, and crack seal.
  • Week 2 Aug. 9-13: Road and driveway apron paving
  • Week 3 Aug. 16-20: Grading, shoulder work, raise guardrail.
  • Week 4 Aug. 23-23: Add rumble strips, striping.

Visit the project website for additional information.